Pinning the roof to its support poles – Part 2

After adding more temporary supports under the roof overhang, Tom climbed on top to decore three 150mm squares for the glass blocks.

p20111124_133454

p20111124_133900

p20111124_134018

Then the glass blocks were inserted…

p20111124_134601

…and the sanded fibreglass poles. Because the holes were 50mm diameter and the poles were 48mm diameter, there was enough space to compensate for the slight slope of the roof against the two outer poles.

p20111129_142837

With all the glass blocks and poles in position, it was time to check that the height of the roof was equivalent on both port and starboard sides. It was necessary to pull one side down slightly and hold it in position with a rachet strap.

Next, glue was carefully squeezed into the space between the glass and the pole.

p20111129_155020

Once the glue had cured, the poles could be removed…

p20111130_171428

…and guided 10mm holes drilled into each side…

p20111130_171457

…to allow insertion of the carbon rods. The fit was firm enough to require gentle tapping in with a hammer.

p20111130_171952

p20111130_172633

The assembled poles, glass and pins were then glued into their final position. There was also preparation carried out down below in the back beam – I’ll write about this in another post.

p20111130_183907

350mm squares of quadraxial fabric were lowered over the poles and wet out with resin in-situ.

p20111202_153144

p20111202_161147

After curing, fillets and double bias tapes were applied to complete the bond between the poles and the roof.

p20111203_151344

p20111203_155758

These poles extended 1100mm above the roof and will be used to for mounting a wind generator, antennas etc. Our head-sail (only) rig allows us to do this.